Mrs. HELENA KAUSHIK WOMEN'S COLLEGE
Management: Shivkaran Parvati Shikshan Sansthan
Funding: Malsisar Educational and Cultural Trust
MALSISAR -331028 JHUNJHUNU, RAJASTHAN
Phones: (0159) 7576561,7576818.
Fax: (0159)7576593

 FUTURE PLANS : 1999 - 2000

PHASE I : 1999-2004

    Goal                                       Objective                                                           Achievement 


 Open College                      Obtain No Objection Certificate                                Obtained April 12, 1999

                                              Secure Space                                                            Rented Nagaria Haveli
                                                                                                                               Free Use of Joshi Haveli

                                              Appoint Principal and Staff                                        Appointed April to August 1999

                                              Inauguration of the College                                        Wednesday, August 4, 1999

                                              Classes Begin                                                            Thursday, August 5, 1999

                                              Affiliation                                                                  University of Rajasthan

                                              Examination Center                                                   Approved March  2002

                                              Obtain Land for New Campus                                   Government of Rajasthan approves
                                                                                                                               30 acres of land on August 3, 1999
                                                                                                                               Government Orders Transfers of Land
                                                                                                                               on October 28, 1999
                                                                                                                               Land Deed Recorded on
                                                                                                                               November 24, 1999
                                                                                                                               Wire Fence Installed in December, 1999

                                              Landscape Plantings                                                  Continuous from February, 2000

                                              Water Connection                                                     Done in January, 2000

                                              Install Tube-well                                                        Installed February, 2000 and June, 2000

                                              Electric Connection                                                    Done in February and June, 2000

New Campus                        Hire an Architect Architect                                         Selected in January, 2000
                                                                                                                                Site Plans and Building Designs
                                                                                                                                Ready in February 2000
                                                                                                                                Supervising Engineer Selected in
                                                                                                                                April, 2000
                                                                                                                                Service Structures Constructed in
                                                                                                                                June, 2000
                                                                                                                                On-site Engineer selected July, 2000
                                              Foundation Stone Ceremony for
                                              Academic Building                                                      Monday, February 21, 2000

                                              Inauguration of a Computer Lab.                                 Monday, February 21, 2000

                                              A Musical Celebration of the First
                                              Anniversary of the College Inauguration                        Friday, July 14, 2000

                                              Foundation Stone for Hostel                                        Saturday, July 15, 2000

                                              Inauguration of the Centre for
                                              Music and Performing Arts                                          Saturday, July 15, 2000

                                              Award Labour Contract to Finish
                                              Construction of the Front Wing in 2001                       Begin construction in July, 2000

Add Second Year                 60 to 80 New Students in First Year                           July, 2000

Add Third Year                   60 to 80 New Students In First Year                            July, 2001
                                             Hire Additional Faculty                                                July, 2000 and July 2001 and Beyond
                                             Hire Additional Staff                                                    Continuous, as needed

New Building                        Transfer Classes and Offices                                       July 2001
                                              Inauguration of New Building                                      2002
                                              Construction of Other Wings                                       July, 2003 to 2004

Library                                  Hire a Librarian and Expand                                       Beginning in 2000, July, 2001
                                              Collection of Books and Periodicals                            Beginning in 2000

Computerization                   Continuous                                                                 2000 to 2004

Arts and Music                     Add Programs                                                           2001 to 2004

New Degree Programs       BSc (Chemistry, Physics, Bio, Zoology, Maths)            July 2002

Sports Fields                         Begin Development                                                    2002 to 2004

Dormitory (Hostel)               Construction Period                                                   2002 to 2004

Graduate Courses                Add M.A. (Part I)                                                      July 2002
                                              Add M.A. (Part II)                                                     July 2003

Polytechnic College                   Open                                                                    July 2003

Computer Courses                    Certificate Programs                                              July 2002

Proficeincy in English                Extra Courses                                                       May 2002

Energy Development                 Energy Center                                                      July 2002

Job Placements                          Job placement services                                         May 2002

Business Development              Open Center for Entrepreneurship                        July 2003
 
 



PHASE II: 2004 -2009





Sports Complex                    Construction of Gymnasium                                      2004 to 2009
                                               Additional Sports Fields                                           2004 to 2009

Faculty Housing                   Construction                                                             2004 to 2009

Amphitheater                       Construction                                                             2004 to 2009

Academic Centre                 Main Building -Completion                                        2004 to 2009

New Programs                     Add More Optional subjects including
                                              Technical and Vocational Courses 12                        2004 to 2009
                                              College of Health Sciences
                                              Business School